The provisional schedule
Generate a lot's provisional schedule from the DCE, read its summary, shift or regenerate it, then download it for Microsoft Project.
Updated on November 7, 2026
Vialogic builds the lot's provisional schedule from the DCE, you review and adjust it here, and it is attached to your bid. It can also be downloaded for Microsoft Project. It opens from the Provisional schedule card of the overview of the tender page, with Open the schedule, or from its line on the submission page: Generate the schedule while it does not exist, Open the schedule afterwards. It stays to do there as long as it is not generated, misses the deadline set by the tender documents or still has durations to confirm; when the tender rules, read in full, do not ask for a schedule, it is optional there as long as it is not ready. Once ready, it goes into the offer's archive (see Export the tender).
Generate the schedule
Two things must be set beforehand: your company's working days and hours (see The schedule calendar), and a rate or a duration for each line of the bill of quantities (see Schedule rates and durations). As long as the working days and hours are missing, Generate the schedule stays unavailable and the page leads to their card with Fill in the working hours; as long as a rate or a duration is missing, the page asks for it under the button, where you give it directly; what cannot be given there leads to the brief page.
- Choose the Start date (notice to proceed): the date of the notice to proceed that starts the preparation period, then the works. It is an assumption, since the notice to proceed is not known yet; Vialogic suggests two months after the bid deadline. When the tender dates the works of the first phase (« Juin 2027 »), an earlier date is moved back at generation so that the preparation period ends when those works open: a point of attention says so, and Shift the schedule remains available.
- Click Generate the schedule.
The generation reads the deadlines imposed by the DCE, the quantities of the DQE or the DPGF and the CCTP, then builds the tasks: one task per line of the bill of quantities, with the rate or duration retained for that line, without estimating anything. A line is neither split nor merged with another. It imposes the trade's order between operations: in rehabilitation, for example, cleaning and inspection before the main sewer lining, then the Réouverture des branchements au robot (robotic reopening of the connections, added if missing), then the lining of the connections; in a trench, excavation, laying, backfill, tests, then reinstatement. A contrary link is removed and reported as a point to watch. When the tender splits the works into distinct phases (« 1ère phase », « 2ème phase » in the DPGF lines), the phases follow one another: a « Début des travaux de la phase 2 » milestone waits for the end of phase 1, and it never falls before the month the tender gives those works (« Juin 2027 »). When the tender gives each phase its own preparation period, phase 2 has its own, a « Période de préparation de la phase 2 » task that ends when its works open. A season (« Printemps / Été 2028 ») sets no date: a point of attention asks you to set it on that milestone, with Dates. Variant lines are not in this schedule, which is the base solution's. Fixed-price effluent bypass, ventilation and lighting cover the works of their phase from start to end. For a structure rehabilitated with sprayed render, cleaning and demolition come before sealing water ingress, then cracks, then spraying. Resources are your company's crews (your costs) and your fleet: a fleet machine is never used more times the same day than you own, the same crew never on more than four tasks at once, and a point of attention names the crews the schedule works in several units the same day. A line the generation did not take up gets the resources of the neighbouring task in the same chapter, to check.
It takes three to six minutes and goes on if you leave the page. Only the Technical and Management roles, on an active subscription, can start it; if a colleague already started it, the page reloads and shows the generation in progress.
What the screen shows
The screen reads from top to bottom: the summary, the Gantt chart, then, folded under the chart, Deadlines read in the tender documents, resources and points of attention (see Deadlines, resources and points to watch).
The summary gives the works period, the contractual deadline and whether it is met ("Completion deadline met" or "Completion deadline not met"), the share of DQE or DPGF lines covered by tasks, the number of durations still to confirm (the one of To confirm only, which drops when you adapt a rate or a duration) and the number of durations from your production rates, then a line that says where the durations come from. It also carries the Start date (notice to proceed) with Shift the schedule, Download for Microsoft Project and Regenerate the schedule. When you deleted a task whose bill lines no other task carries out, the summary names them: "1 bill of quantities line is no longer covered by a task (deleted by hand): 1.2 Chemisage DN200". When the tender gives each phase its own deadline, the summary adds one line per phase: its works, the deadline and whether it is met. That deadline runs from the end of the phase's preparation: the site setup that follows it counts.
Shift or regenerate the schedule
In the summary, change the Start date (notice to proceed) then click Shift the schedule: every date is recomputed without regenerating the schedule; a deadline counted as a duration follows the new start.
Regenerate the schedule rebuilds everything from that same date, for example after a DCE change. The rates and durations retained in the brief and the rates and durations adapted here task by task (lump sums included) are kept, including on a task the regeneration renamed (an attention point says so); one whose task disappeared is flagged. The other changes made by hand (links, tasks added or deleted, renames, moves, imposed dates, resources) are not kept: under the button, the page counts them, and before regenerating a window warns you, for example "3 changes made by hand will not be kept". Regenerate anyway starts the regeneration; the new schedule recalls it in its points to watch.
During the regeneration, the previous schedule stays on screen, read-only, with "Regeneration in progress: this schedule will be replaced when it ends.". If it fails, the schedule stays on screen with the failure message.
The schedule and the technical proposal
Make the schedule before the technical proposal: the proposal reuses its timeframe, phases, rates and resources. If you change the schedule after the drafting (start date, rate, regeneration), the drafted proposal flags it with a banner.
After the work: site feedback
For a won tender, the Site feedback card shows under the schedule. For each task that follows one of your company's rates, enter the quantity done (empty: the planned quantity), the actual days and the number of crews. The actual rate, quantity ÷ days ÷ crews, shows as you type. Save the feedback adds it to the rate: in its average, it replaces this tender's forecast. A task without actual days changes nothing.
Download it for Microsoft Project
Download as PDF saves the schedule attached to the bid, the same as in the submission archive. Download for Microsoft Project saves an XML file. In Microsoft Project, open it with File then Open, choosing the "XML" type. Tasks keep their links, milestones, resources grouped by company and the site calendar with public holidays; the tasks added, links, imposed dates and resources changed in Vialogic are in it too. This calendar uses your working days and the working hours of My company, as they are when you download; with no working hours set, it uses those of Project's standard calendar (8:00-12:00 and 13:00-17:00).
The file is written for the buyer, to whom you attach it: task notes only give the quantity, the rate (per crew and in total), the imposed dates and the contractual period of the preparation, without Vialogic's internal mentions ("estimated", "to confirm"). Each machine is a single resource, at the capacity of your fleet: Microsoft Project flags the day the schedule asks for more. A crew, or a rented machine, has as capacity the number of units the schedule uses the same day. A rented machine carries "(location)" in its name. The contractual deadline is set on the final milestone; a typical purchase order only has one if the DCE sets its period. The same file goes into the tender's archive, in the sources folder, next to the schedule as a PDF.
Related articles
- Schedule rates and durationsWhat the schedule needs before it can be generated: a rate or a duration per bill line, or a duration per phase, and where each duration comes from.
- Read the Gantt chartRead the schedule's Gantt chart: columns, bars and markers, timescale, filters, keyboard navigation and task details.
- Adapt a duration to this siteChange the rate or duration of a schedule task for this tender only, by stretching its bar, with the keyboard or from its details.