The brief of a tender

Answer the questions that prepare the technical proposal and the schedule, then validate the brief, at any time after the import and the lot choice.

Updated on November 7, 2026

The brief gathers the questions that prepare the technical proposal and the schedule. It has its own page, opened from the tender page's Progress (Open the brief), from the proposal or from the schedule, as soon as the DCE is read and the lot chosen. Nothing waits for it: the proposal, the schedule, the financial offer and the submission start without it, and rely on the answers already given.

Answer the questions

On the first opening, Vialogic prepares the brief from the DCE. The questions are grouped by theme, each showing how many are unanswered; on a large screen, the list of themes stays in view as you scroll through the questions. The bid submission rules (checks, commitments, prices) are not among them: they are settled at submission (see Submission questions).

Each answer is saved at once: Confirm what the tender says, choose a suggestion, or write your answer then Save the answer. Mark a question that doesn't concern you Not applicable. When the question carries a commitment type, choose Firm or Indicative. When several answers are facts read in the tender documents (deadline, site visit, variant…), Confirm the N tender facts, above the themes, confirms them at once; a suggestion drawn from your documents is always confirmed one by one.

A proposal drawn from your documents is split into parts (table, steps, key figures, schedule), each with its sources. Tick the ones to keep, fix them with Edit, fill in what is missing with Write, then click Use. If a colleague answered meanwhile, the brief reloads with their answer; switching themes does not lose text being typed. A brief that could not be prepared offers Prepare the brief again.

Rates and site phases

Two questions of the Schedule theme prepare the provisional schedule:

  • Les conditions de ce chantier ralentissent-elles la production ? (do this site's conditions slow production down?) lists the conditions found in the CCTP, the CCAP or the RC (maintained traffic, imposed hours, networks to protect, difficult access…), each with the sentence of the tender that grounds it;
  • Quelles cadences retenez-vous pour les activités principales de ce chantier ? (which rates do you keep for the main activities?) proposes a table with one row per line of the bill of quantities, its quantity, the Référence (reference) and the Cadence retenue (retained rate). A quantified line expects a rate; a lump-sum line (quantity "1 Ft") expects a duration in days ("5" or "5 j"). The reference is your company's matching rate or duration, or "Aucune cadence de l'entreprise : à donner" (no company rate: to give; "Aucune durée de l'entreprise : à donner en jours" for a lump sum): the retained rate is then empty ("?"). Correct or fill in that column with Edit; a column copied from your spreadsheet and pasted into a cell fills the following rows.

When the DCE has no quantified line, the rates question gives way to Quelle durée retenez-vous pour chaque phase de ce chantier ? (which duration do you keep for each phase of this site?): each Phase, Ce qu'elle couvre (DCE) (what it covers), the Référence and the Durée retenue (j) (retained duration), to give in days.

The schedule uses these answers: a rate retained here takes precedence over your rates and stays in place if you regenerate the schedule. The schedule won't generate while a quantified line has no rate, or a lump sum no duration, and then leads you here. Saving the answer also puts these rates in your production rates.

Validate the brief

You answer the brief only once. Until it is validated, the bar at the bottom of the page carries Validate the brief. It stays inactive while any question is unanswered, with the number left next to it ("2 questions to settle before validating") and Go to the first one, which opens its theme and takes you there.

Validate the brief opens a confirmation: all the brief's answers will be locked; the submission questions are not part of it and can still change until the tender is submitted. Validate for good validates the brief: "Brief validated." An incomplete brief (part of the tender rules could not be read) cannot be validated.

The page then recalls "Brief validated on …: it is locked.". Each question is shown read-only, marked Validated. Two exceptions, born after validation, keep their buttons with the mention "Final once settled" and are confirmed with Save for good: the rows the schedule adds to the rates table (or to the phase durations table), and the new questions of a corrigendum, which Add the new questions from the DCE rereads without touching the validated answers. A question whose excerpt changed shows "The corrigendum changed this excerpt"; a question the DCE no longer asks is marked "No longer asked by the DCE".

Validation also calculates the tender's competitiveness, shown on its page: see The tender page.

Who can do what

Answering and validating the brief need the Technical or Management role; the other roles read it, with "Read-only: the brief is answered with the Technical or Management role." During a subscription pause, or on the free plan with existing data, the page is read-only too.