Read the Gantt chart
Read the schedule's Gantt chart: columns, bars and markers, timescale, filters, keyboard navigation and task details.
Updated on October 11, 2026
The Gantt chart of the provisional schedule shows the tasks as in Microsoft Project. To change it, see Adapt a duration to this site and Edit the schedule in the Gantt chart.
The list and the timeline
On the left, the list takes Project's columns: ID, Task, Duration, Start, End, Predecessors and Resources. Predecessors are written as in Project: the task number, followed by the link type except for a plain finish → start link, then the lag ("3; 5SS; 7FS+2 d"). On the right, the timeline places each task on a two-level timescale. Both scroll together up and down, the timeline alone left and right; drag the divider between them to widen the list.
Bars and markers
A task is a solid bar, red when it is on the critical path (it drives the end of the works). A phase is a bracket bar, from the start of its first task to the end of its last; a milestone, a diamond. The Préparation phase opens the schedule: the preparation period and, when the DCE places them there, the checks before the works (camera inspection, survey, setting out); no work starts before it ends. Wastewater bypass is a single continuous task, hatched: its dates follow those of the works it covers.
A pale bar with a dotted border flags a duration to confirm, "×2" a task with two crews. To the right of each bar, its resources; to the right of a milestone, its date. Non-working days (weekends, public holidays, site closures) are greyed out, a dotted line marks the contract deadline when there is one (the legend only mentions it then), another one today. A blue bracket marks a task's start no earlier than date; a small downward arrow, its finish no later than date, green when it is met, red otherwise. Legend, above the chart, unfolds to recall these markers.
Arrows connect linked tasks (finish → start, start → start, finish → finish or start → finish), lag included. They stay discreet: hover or select a task to bring its own forward.
Timescale, filters and keyboard
Day, Week and Month change the timescale; Fit all fits all the works in the width of the timeline. The chevron in front of a phase collapses or expands it. To confirm only, shown while some durations remain to confirm, keeps only those tasks, under their phases.
In the list, the ↑ and ↓ keys move from one task to another, ← and → collapse or expand a phase (and, if you can edit the schedule, move from one cell to another: name, duration, predecessors). On a phone, the list takes the full width with the name and the duration, without timeline or zoom: tap a task to open its details.
Task details
Double-click a task, in the list or on its bar, or select it and press Enter: a panel opens. It gives its dates, its duration, its Total slack (in red when negative), its production (the bill quantity and the rate, "400 lm at 80 lm per day"), the Bill of quantities lines it carries out (price number, label and quantity), its note, its resources, its imposed dates, its predecessors and its successors, then the actions it allows. A schedule generated before 10 October 2026 does not have the bill lines of its tasks: regenerate it to see them.
Its badges say where its duration comes from: Duration retained in the brief or Company duration for a lump-sum task or a phase, Duration from the bill for a line counted in days in the bill. Added by hand marks a task inserted in Vialogic, Critical path a task that drives the end of the works, Deadline date missed a task that ends after the date imposed on it; the panel then says by how much.
Related articles
- The provisional scheduleGenerate a lot's provisional schedule from the DCE, read its summary, shift or regenerate it, then download it for Microsoft Project.
- Adapt a duration to this siteChange the rate or duration of a schedule task for this tender only, by stretching its bar, with the keyboard or from its details.
- Edit the schedule in the Gantt chartLink, insert, delete, rename and move schedule tasks, set imposed dates and resources, undo a change.