Your production rates

Your working days and hours, what a crew or a machine of your company produces per day and the duration in days of your lump-sum services: read in your documents, given in the brief or entered, used by the brief and the schedule.

Updated on November 7, 2026

A production rate says what a crew or a machine of your company produces in one day, for example 40 lm of laid pipe. A rate in the "d" unit is a duration: the number of days a whole lump-sum service takes, a site set-up or a demobilisation for example; it shows as "5 d". Each tender's brief offers them to you, and the provisional schedule takes them one for one, line by line of the bill of quantities, without estimating anything. Vialogic makes none up: they all come from your company.

Working days and hours

At the top of the screen, the Working days and hours card says how your company works: the provisional schedule counts your working days, and the Microsoft Project file uses your working hours. You choose them; Vialogic sets none.

  • Working days: tick the days of the week your crews work, at least one.
  • Working hours of the day: one time slot, with its Start and End, or two when a break separates them (lunch). Add a time slot adds the second one, Remove the time slot removes one. Time slots follow the order of the day, without overlapping or touching (two time slots that touch make a single one), and none runs past midnight.
  • The total shows under the time slots, for example "Total: 7 h 30 min per day" for 7:30-12:00 and 13:30-16:30. Click Save: an incomplete or inconsistent entry is flagged under the field concerned, before anything is sent. Leaving the page before saving what you entered asks for confirmation.

As long as nothing is set, the card shows "Not set: a bid's schedule can't be generated without them.", with empty fields. Once saved, it sums them up, for example "Saved: Monday to Saturday, 7 h 30 min per day.".

Where your rates come from

  • Read in your documents: Read my documents looks in your technical proposals and method statements for the sentences that give an output per day ("80 lm of lining per day", a "Daily output" table). A manufacturer's or supplier's documents (data sheet, instructions) are not read: their capacities are not yours. A message says how many rates were found.
  • Given in the brief: on a tender's brief page, the rates table has one row per line of the bill of quantities. It asks for a rate for each quantified line and a duration in days for each lump sum, and offers yours when it matches. What you give there joins your rates, named without the line's price number; a duration joins them in the "d" unit (see Rates and site phases).
  • Entered here: Add a rate, or Keep this rate from a schedule task.

Under each activity, the screen recalls where it comes from: "Read in a document", "Given in a brief", "Entered" or "Kept from a schedule".

Confirm what your documents say

Rates read in your documents arrive in "To confirm", with the sentence read and the file ("Read in:"). Only confirmed rates are used by the brief and the schedule.

  • Confirm keeps it as it is;
  • Correct opens the window: saving it confirms it with your corrections;
  • Dismiss removes it, and it won't be proposed again.

A value that learns from your tenders

Each tender that retains a rate, in the brief or through Adapt to this site in the schedule, adds its value. The rate is then the average of its starting value and of these tenders, and the screen says so: "Average of 3 tenders".

After the work on a won tender, its site feedback (Schedule page) gives the rate actually achieved: in the average, it replaces the value planned for that tender.

Changing the value of a confirmed rate sets it by hand: "Entered value (takes precedence)" shows, followed by the tenders' average when there is one. This value prevails until Use the tenders' average, which removes it; that button only shows once at least one tender has given its value. Changing only the conditions or the crew doesn't freeze the value.

What the table contains

Confirmed rates are grouped by trade, those of your specialties (My company › Identity) first, those without a trade last, under "No trade" (without a heading when none has a trade). Each has its activity, its Output per day or duration (one crew or machine), for example "80 lm/d", the crew or machine that achieves it and its conditions (diameter, depth, ground type…). A duration shows in days ("5 d"), with the mention "Duration in days".

In the window, the Trade is chosen among your specialties and the trades already in the table, the Unit likewise (lm, m², m³, u, t, kg, lump sum, h, d); Other… lets you type another value. To save a duration, choose the d (duration in days) unit: the field becomes Duration in days (one crew or machine), and you enter the number of days of the whole service, 5 for 5 days. Machine from your equipment picks the machine from your equipment: Crew or machine then takes its name. A machine archived since stays shown, marked "archived, no longer offered". Delete removes a rate permanently, after confirmation: it will no longer be used for your next briefs or schedules.

With the Technical or Management role, on an active subscription, you can change the working days and hours and the rates; other members can view them.