Deadlines, resources and points to watch

The folded section under the schedule's chart: deadlines read in the DCE, points to watch, resources by company, and how the calendar counts days.

Updated on October 11, 2026

Under the chart of the provisional schedule, the folded section Deadlines read in the tender documents, resources and points of attention says what the schedule rests on and what remains to check. Its title counts the points of attention; click it to unfold it.

Deadlines read in the DCE

Each deadline constraint shows with the DCE sentence it comes from and its document, in the DCE's unit (working days, business days (Mon–Sat), calendar days, weeks or months), including "Preparation included in the completion period" or "Preparation not included in the completion period" when the DCE says so. If it says nothing, Vialogic applies the rule of the CCAG Travaux (preparation included), except for a preparation as long as the works, which is added to it; a point to watch says so.

Points to watch

They say what remains to check, for example a completion deadline not met, and are recalculated after every change to the schedule. They also flag a finish no later than date a task does not meet, and the bill lines a deletion left without a task. Two points concern your working days and hours: they are not set, or the days changed since generation (then regenerate the schedule); both end with the link Set the working days and hours (My company › Production rates).

Meet the deadline

To meet the deadline, generation runs tasks in parallel and, if needed, puts several crews on a task (four at most). An added crew comes whole, with its machines, each carrying its rank ("Hydrocureuse 26 t (2ᵉ)"); the task shows it ("2 crews to meet the deadline") and its note explains why. A rate confirmed in the brief stays the rate of one crew: crews are added, it is never made to produce faster.

Machines come from your equipment when it is entered: a reinforcement never asks for more machines than your fleet has, and two tasks competing for the same machine run one after the other. A machine missing from your fleet is rented: it shows "rented" in the task details and in Resources by company. If nothing is enough (a single machine, a fixed duration that is too long such as drying), the schedule stays "Completion deadline not met" and a point to watch names what blocks.

Resources by company

In a consortium or with subcontractors declared in the DC2 and the DC4, this part gives the crews and plant each company brings. In Microsoft Project, it is the "Group" field of each resource.

The schedule calendar

The schedule's calendar counts your company's working days, chosen in My company › Production rates (see Working days and hours) and fixed at generation; as long as they are not set, Generate the schedule stays unavailable and the page leads to their card with Fill in the working hours. The calendar also skips public holidays in mainland France. Task durations are therefore in your working days.

The DCE's deadlines, however, are always counted on the legal calendar, whatever your working days: working days ("jours ouvrés") from Monday to Friday, business days ("jours ouvrables") from Monday to Saturday, public holidays excluded. A Saturday worked helps meet the deadline, it doesn't bring it closer.