Schedule rates and durations
What the schedule needs before it can be generated: a rate or a duration per bill line, or a duration per phase, and where each duration comes from.
Updated on November 7, 2026
The provisional schedule estimates no duration: it takes them from the tender's brief or from your production rates. As long as some are missing, it is not generated.
One rate per bill line
The tender's brief asks, in its rates table, for a rate for each quantified line of the DQE or the DPGF and a duration in days for each lump-sum line (its quantity reads "1 Ft" there). Each row of the table carries the price number of the bill line, so you can find it in your DQE; beyond thirty lines, the table goes on in "(suite 2)", "(suite 3)"… parts. The schedule takes these values one for one: the one given in the brief for the line, otherwise a matching confirmed rate or duration among your production rates. A line counted in days in the bill (a 20-day pump hire, for example) already carries its duration: nothing to give.
As long as some are missing, the schedule doesn't start: the page asks for them under the button, right where you are. Its heading says for example "To generate the schedule, give the rate or duration of the 3 price-schedule lines", then it shows one box per line, with its quantity and the expected unit; the box is pre-filled with your rate or duration when you have one ("Suggestion: 3 j (vos cadences : « Chemisage »)"), or with a deadline the DCE writes for that phase, to check: nothing is saved without you: a daily rate in the line's unit ("lm/day"), or days for a lump sum. Save and generate the schedule saves them in the brief, then generates the schedule. Each box expects a number greater than zero. Rates and durations given this way also join your rates in My company. If a line cannot be filled here, the page names it and leads to the brief page with Give them in the brief.
A rate is found again on its own on another tender when the line has exactly the same label. When the label only differs by the name of the structure or place at the end of the line ("Reprise étanchéité intérieure du BARET" after "… du RAMONAILS"), Vialogic suggests your rate: the box is pre-filled and the line says "Suggested from your rate “…”: check it". The unit must also be the same. A rate suggested this way never enters the schedule without Save and generate the schedule; in the brief, the Reference column writes it "cadence proche", and the retained value is still to give.
Prepare the rates question
A brief prepared earlier may have nowhere to receive these values: it lacks the rates question, or its table grouped the bill lines into a few activities, or it lacks the lump sums or the reopening of the connections. The page then offers Prepare the rates question, for the Technical and Management roles only: Vialogic adds the question, or the missing lines (at the end of the table, then in "(suite)" parts), to the brief without touching the other questions or the answers already given, then the boxes to fill appear. If the brief is not prepared yet, prepare it first: it asks the rates question.
A rates question already answered reopens: the values you gave stay, only the added lines are left to fill in. On a validated brief, which is locked, these lines are one of only two things still to settle: they arrive empty and are filled in once each, a saved rate can no longer change. A value the schedule cannot read (a rate in another unit than the quantity, a duration not in days for a lump-sum line) counts as an empty cell: it can be corrected, once. A grouped activity you had answered covers its lines only when the match is certain (same operation, same unit, same total quantity); otherwise, its lines are added, to fill in. If no line of the bill needs a rate or a duration, the notice says so and the brief is not changed.
Without quantities, one duration per phase
When the DCE has no quantified line (no bill, or a schedule of unit prices without quantities), the brief instead asks for the duration of each phase of the works: Quelle durée retenez-vous pour chaque phase de ce chantier ? (which duration do you keep for each phase of this site?). The phases come from the DCE, each with the sentence that describes it; you give their duration, in days.
As long as a phase has no duration, the page asks for it under the button: "To generate the schedule, give the duration of the 4 site phases", then one box in days per phase, with what it covers according to the DCE (for a framework agreement with purchase orders, the duration of a typical order). Save and generate the schedule saves them in the brief, then generates the schedule. On a validated brief, a saved duration can no longer be changed. If the brief does not have this question yet, Prepare the phase durations question reads the phases in the DCE and adds it to the brief, without touching the rest, then the boxes appear. If this reading fails, nothing is written: try again.
The schedule then makes one task per phase, placed in a phase of the same name, with the duration given in the brief (Duration retained in the brief badge). Detail it in the chart: insert your tasks into the phase, then delete the original task if you wish (see Insert, delete, rename, move). These durations also join your rates in My company, under the phase's name.
A framework agreement with purchase orders
For a framework agreement with purchase orders, these are the durations of a typical purchase order, and the schedule is that of a typical purchase order: the summary shows "Schedule of a typical purchase order under the framework agreement.". This schedule does not take the end of the framework agreement as its deadline, since that date bounds the framework agreement, not each purchase order: without a period set for a purchase order in the DCE, it has no deadline, and the summary says "Period set by each purchase order." instead of the deadline and of "Completion deadline met". If the DCE sets the period of a purchase order, it is counted from the start of the schedule: "End of the purchase order period: …". The start and end of the framework agreement stay in Deadlines read in the DCE.
Where each duration comes from
A duration is the quantity divided by a production rate: the one retained for this site in the brief (Rate confirmed in the brief), otherwise the matching one among your confirmed rates (Company rate). A lump-sum line takes the duration in days retained in the brief, otherwise the matching one among your rates. A phase takes the duration retained in the brief, otherwise the duration among your rates that bears its name. Generation also takes into account the site conditions, phasing, crew and equipment confirmed in the brief (see Rates and site phases).
The Estimated rate and Estimated duration badges now only appear on an earlier schedule: those tasks stay to confirm. When no duration comes from your rates and no machine comes from your equipment, the summary says so: rates are estimated and do not reflect your actual resources. To change a rate or a duration for this tender only, see Adapt a duration to this site.
Related articles
- The provisional scheduleGenerate a lot's provisional schedule from the DCE, read its summary, shift or regenerate it, then download it for Microsoft Project.
- Your production ratesYour working days and hours, what a crew or a machine of your company produces per day and the duration in days of your lump-sum services: read in your documents, given in the brief or entered, used by the brief and the schedule.
- The brief of a tenderAnswer the questions that prepare the technical proposal and the schedule, then validate the brief, at any time after the import and the lot choice.