Adapt a duration to this site

Change the rate or duration of a schedule task for this tender only, by stretching its bar, with the keyboard or from its details.

Updated on October 11, 2026

From one site to another, the same activity doesn't go at the same speed: maintained traffic, urban areas, existing networks or imposed hours slow production down, a clear site speeds it up. The schedule therefore lets you change what is decided for this tender: the rate of a quantified task, the duration of any other task (estimated, lump-sum retained in the brief or from your company, written in the bill, or added by hand), and the start. Vialogic then recalculates every date of the provisional schedule, without regenerating it. These actions need write access (see Edit the schedule in the Gantt chart).

Stretch a bar

  1. Hover the right edge of a bar that can be changed: the pointer becomes a double arrow.
  2. Drag it. The bar grows or shrinks to the day (a non-working day doesn't count) and shows the proposed duration, with the resulting rate for a quantified task ("5 d · 80 lm/d").
  3. Release: a window sums up the change, for example "400 lm in 5 d = 80 lm/d". Apply saves it; Cancel, Esc or a click elsewhere puts the bar back in its place.

For a quantified task, the new duration becomes a rate for this site: the quantity divided by the number of days. On a task with several crews, the window also gives the rate of one crew, and the number of crews does not change. Bringing the bar back to the reference duration clears the site's rate. For a task without a quantity, the new duration becomes the site's duration. For a lump-sum task, the window says so: the duration replaces the one retained in the brief or the one from your production rates for this tender, and, when the task uses a duration from My company, it also counts towards that duration, like an adapted rate.

Enter a duration with the keyboard

With the keyboard, click the duration of a task that can be changed in the list (or select the task, move to the Duration column and press F2), type the number of days, then Enter to save it or Esc to cancel. As in Project, clicking elsewhere keeps a valid entry; a wrong entry stays open with its error. The duration of a lump-sum task goes through the same confirmation window as a stretch. Dragging the start milestone moves the start of the schedule, with the same window. During the recalculation, the task fades in and out; if saving fails, a message says so and the bar goes back to its place.

From the details

  1. Open the details of a quantified task, then click Adapt to this site.
  2. Enter the Rate per day. The window recalls the reference and shows the resulting duration. On a task with several crews, enter the Rate of one crew: the window recalls the reference per crew and the total ("4 crews, i.e. 6 u per day in total"), and the number of crews does not change.
  3. Click Save: the task's duration and every date are recalculated, without regenerating the schedule.

The task then carries the Rate for this site badge instead of its source's, and its production gives the site's rate followed by the reference ("reference: 40 lm per day"). Back to the reference clears the site's rate. When the task uses a rate from My company (directly or through the brief), the window says so: this site's rate counts in that rate's average, instead of the one given in the brief for this tender (see Your production rates). Otherwise, your rates don't change.

In the details of a task without a quantity, Adapt the duration sets its duration in working days for this site: an estimated duration, a lump-sum duration retained in the brief or from your company, a duration written in the bill, or that of a task added by hand. The window says what becomes of the duration. The task then carries the Duration for this site badge; Back to the reference restores the original duration (a task added by hand has none). Dates are recalculated the same way, and the technical proposal reuses this duration.

In the details of a task whose rate is estimated, Keep this rate opens the entry window of your production rates, prefilled: the activity (the task's name), the unit, the rate the task is computed on (the site's rate if you adapted it), brought back to one crew when the task has several to meet the deadline, and its first crew or machine. Choose the Trade (required), then Save.

What cannot be changed

A frozen bar has no edge to stretch. Hover it to find out why, or click it: a window says so, with View details.

  • A phase follows its tasks, a milestone is a point in time, a continuous task follows the tasks it covers: neither their duration nor the links of a continuous task can be changed.
  • Another fixed duration, such as the preparation period, cannot be changed.