Edit the schedule in the Gantt chart
Link, insert, delete, rename and move schedule tasks, set imposed dates and resources, undo a change.
Updated on November 7, 2026
As in Microsoft Project, everything can be changed in the Gantt chart of the provisional schedule: links, tasks, their order, their imposed dates and their resources. Each change is saved straight away and every date is recalculated, without regenerating the schedule. If a colleague changed the schedule in the meantime, your change is not applied: the schedule is reloaded and a message says so, so you can redo it if needed.
These actions need write access. Without it (you don't have the Technical or Management role, or the subscription is paused) and during a regeneration, the chart is shown the same way and nothing can be changed in it: no duration, link, task or right-click menu. To change a rate or a duration, see Adapt a duration to this site.
Link tasks
- Hover a bar: a round handle appears at its end.
- Drag it onto the bar of the task that must follow. The target row is highlighted when the link is possible.
- Release: the finish → start link is added, with no lag.
Double-click a link's arrow, or choose Edit next to a predecessor in the details, to change its type (finish → start, start → start, finish → finish, start → finish) and its Lag in working days, negative for a lead; Delete the link removes it. Add a predecessor, in the details or the right-click menu, adds one from a task chosen in the list.
The Predecessors column can also be typed, as in Project: move to the column and press F2, or double-click it, then type the task numbers separated by semicolons (or commas), each followed by the type except for a plain finish → start, then the lag: "3FS+2 d; 5; 7SS-1". The French types (FD, DD, FF, DF) are accepted too. Leaving the column empty removes every predecessor.
A phase is not linked: link its first or last task. A continuous task can precede another task, but takes no predecessor. A link that would close a loop is refused, and the message names the tasks of the loop, for example "“Curage” → “Chemisage” → “Curage”".
Insert, delete, rename, move
Insert, at the top of the chart, or the Insert key on a selected task, opens a window: choose A task (its name and its duration in working days, which you give), A milestone or A phase. A phase gets its first task straight away: the schedule never keeps an empty phase. As in Project, the insertion goes above the selected task, in its phase, or at the end of the schedule with no task selected. The inserted task carries Added by hand: link it to place it in time.
Delete, or the Delete key, asks for confirmation and says the consequences: a phase goes with its tasks, the tasks that followed the deleted task will wait for what it waited for, and the bill lines no other task carries out will no longer be covered (the summary and the points to watch then name them).
To rename a task, double-click its name in the list, or move to the name column and press F2, then Enter. The details also have a Name field.
To move a task, drag its row in the list: a line places it above or below another, a highlighted phase takes it at the end. Move up, Move down and Change phase, in the right-click menu or under Place in the schedule in the details, do the same. A phase moves with its tasks; an emptied phase disappears.
Right-clicking a row or a bar opens the menu that gathers these actions: Task details, Insert a task, Insert a milestone, Insert a phase, Rename, Add a predecessor, Move up, Move down, Change phase and Delete.
Imposed dates and resources
In the details of a task or a milestone, Imposed dates gives a Start no earlier than (the task does not start before) and a Finish no later than (the date by which it should be finished), each with its date picker and Clear, then Save dates. The start no earlier than date places the task; the finish no later than date never moves it: when it is not met, the slack becomes negative, the mark turns red on the timeline, and the details and the points to watch say so.
Under Resources, tick the crews and machines of the schedule the task uses, or name a New resource choosing its type (crew or equipment), then Save resources. A phase has neither imposed dates nor resources: they go on its tasks.
Undo and history
Undo, at the top of the chart, or Ctrl+Z (⌘Z on a Mac) outside an input field, undoes the last change, and pressed again, the one before. The button is greyed out when there is nothing to undo. There is no redo: do the action again. Only the last 50 changes can be undone.
History lists the changes to the current version of the schedule, most recent first: who, when, and what was done in one sentence. An undone change is struck through; a change a regeneration would not keep says so (see Shift or regenerate the schedule).
Shortcuts
Shortcuts, at the top of the chart, recalls the mouse gestures (stretching a bar, linking it by its round handle, the right click) and the keys of the list: Insert inserts a task, Delete deletes it, F2 edits the active cell (name, duration or predecessors), Ctrl+Z undoes, the arrows move from one task or cell to another, Enter opens the details and Esc abandons an entry or a drag.
Related articles
- The provisional scheduleGenerate a lot's provisional schedule from the DCE, read its summary, shift or regenerate it, then download it for Microsoft Project.
- Read the Gantt chartRead the schedule's Gantt chart: columns, bars and markers, timescale, filters, keyboard navigation and task details.
- Adapt a duration to this siteChange the rate or duration of a schedule task for this tender only, by stretching its bar, with the keyboard or from its details.