The operation price study
Price the whole operation, tasks, crews, plant, supplies and services, then spread its price over the lines of the bill of quantities.
Updated on October 15, 2026
For a bill of quantities (DQE), a lump-sum schedule (DPGF) or a fixed-price job, you price the whole operation before spreading its price over the lines: that is what the price study does. It opens from the Operation price study card of the financial offer, one per lot. Vialogic calculates with your costs, your production rates and your price build-up; it never sets a price. Each change saves the study, and the calculation is redone at once.
Starting from a base
While the study has no task, Start from a base offers two starting points. Reuse the schedule creates the tasks of this tender's schedule: lines, quantities, rates, priced crews and machines, and its duration. Reuse this study copies another tender's study at today's costs; its lines are found here when the text is the same. A line that cannot be found stays to attach, a quantity from the other site stays to enter: the study cannot be applied before. You see what will be reused before confirming.
Tasks
A task counts its days: its quantity divided by its output, rounded up to the day, or set days (set-up, demobilisation). Its crew works those days, for the length of a working day; so does its plant, according to its use rate. Create one task per line creates one for each priced line, with the company production rate that matches it.
Supplies and services
A quantity is entered, counted per unit of the lines (1.03 m of liner per metre), or by the study's duration: days, weeks, months of hire, calendar days. A supply carries its wastage; all of them can carry a discount.
Spreading the price
An element assigned to a line goes to it. Shared, or common to all base lines, it is spread pro rata to their cost or their quantities. The price is then spread by cost type, each line bearing the overheads of its own costs, or with a single coefficient, like a quote by item. Rounding applies to the total price of the base solution, before contingencies: a variant or option line keeps its price before rounding, and does not change those of the base.
Settings
Site worked away from base switches your crews to their working-away cost. The working day, days per week and duration use the company's when left empty. Customise for this study adapts the price build-up to this site, without changing the company's.
Applying the prices
The summary gives the direct cost, the price, the margin, the duration and the points to review: a blocking point prevents writing the prices. Note your assumptions and gaps there: they are shown in the financial offer's summary. Download the workbook gives the study as a spreadsheet: each amount and its recalculation in formulas, sheet by sheet, ready to justify your price. Apply the prices writes each priced line's unit price into the grid, replacing a price given another way; a line the study no longer prices loses the price an earlier version gave it, and the confirmation window says so. Then regenerate the templates.
Related articles
- The financial offerHave the price templates of the DCE read, give one price per item or paste them from your spreadsheet, then download the filled and checked templates.
- Your costsThe hourly cost of your crews and qualifications, the cost of your machines, the price of your materials and services, and how your price is built up: the basis of your prices from direct cost.
- Your production ratesYour working days and hours, what a crew or a machine of your company produces per day and the duration in days of your lump-sum services: read in your documents, given in the brief or entered, used by the brief and the schedule.