Your costs
The hourly cost of your crews and qualifications, the cost of your machines, the price of your materials and services, and how your price is built up: the basis of your prices from direct cost.
Updated on October 13, 2026
Construction companies price from direct cost (déboursé sec): what a piece of work really costs (labour, equipment, materials, subcontracting), to which their costs and margin are added. The Costs tab of My company gathers these costs once for all your tenders. Vialogic suggests none: it only calculates with yours.
What you enter
- Labour: the loaded hourly cost of each qualification (site manager, worker, machine operator…), never that of a person, and, if you have one, its working-away cost. The roles in your team without a cost are listed: one click opens the entry.
- Crews: the crews that work together ("1 foreman + 3 workers") and their hourly cost, standard and working away. Enter it if you know it; otherwise it is calculated from the qualifications of its make-up.
- Equipment: the hourly or daily cost of each active machine of the Equipment tab, depreciation and daily running costs included.
- Materials and supplies: the purchase price excl. VAT, the unit, the losses (offcuts, breakage) and the supplier.
- Services: subcontracting, hire and sundry costs at a unit price (CCTV inspection, skip, bailiff's report…).
- Price build-up: your costs on production (labour and plant: site costs, overheads, supervision…), compounded or added up; your costs on supplies; your costs on subcontracting and hire; your margin, on the total cost or as a markup rate; your contingencies; the rounding of a study price. The coefficient of each type is shown as you type.
Each cost carries its date. After a year, it is marked "To review": a purchase price ages.
From your spreadsheet
Paste from a spreadsheet takes your rows at once, under each heading. What is already costed (same name) gets the new price; an unreadable row is set aside and reported. For working-away costs, also copy the header row, with a "GD" column and an "HGD" column: your crew rates paste as they are. A machine's cost is matched to your fleet by its name; a machine not in your fleet is not created.
In your bids
In the financial offer of a tender, Breakdown builds the price of a line from these costs and your price build-up. A crew counts in crew hours: from a production rate, its hours per unit are the length of a working day divided by the day's output. It keeps a copy of them: a cost changed here is flagged on the tender, never reapplied without you. A breakdown already built can be reused on an identical line of another tender, at today's costs.
Related articles
- Your equipmentYour machines and equipment, entered once in My company or suggested from your documents, used by the DC2, production rates, the schedule and the technical proposal.
- Your production ratesYour working days and hours, what a crew or a machine of your company produces per day and the duration in days of your lump-sum services: read in your documents, given in the brief or entered, used by the brief and the schedule.
- The financial offerHave the price templates of the DCE read, give one price per item or paste them from your spreadsheet, then download the filled and checked templates.